Detour: Murdoch Avenue Bridge to Close April 23

The bridge, which wil remain closed for six months, is being replaced because it is functionally obsolete and structurally deficient.

Plan on a little extra time to get where you're going if you use the Murdoch Avenue Bridge in or travel in areas around it.

Starting Monday, April 23, the bridge over the Burlington Northern Santa Fe Railroad between Interstate 44 and Big Bend Boulevard will close. The closure also includes the ramp onto westbound I-44 from Murdoch Avenue.

The bridge is being replaced because it is functionally obsolete and structurally deficient, Webster Groves officials say. However, it is not dangerous.

Find out what's happening in Affton-Shrewsburywith free, real-time updates from Patch.

Kozeny Wagner, the contractor, has 180 days to complete the project. The maps in the attached .pdf file show current traffic patterns and detour routes.Β 

The closure has been postponed a couple of times. Originally,Β . However, the contractor was still in the process of getting drawings and demolition plans approved by MoDOT and the Burlington Northern Sante Fe Railroad.

Find out what's happening in Affton-Shrewsburywith free, real-time updates from Patch.

. However,Β  over how long it would take to demolish the bridge.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here

More from Affton-Shrewsbury